Yes. As long as your WBS in Microsoft Project is correct down to the Work or Planning Package level, WBS Process will re-identify new or moved tasks to match the Work or Planning Package they now report to hierarchically.
No. The Estimates / Reports tool creates its output by examining your resource assignments and the WBS of the tasks to which they are assigned. Tasks that are not resource-loaded do not impact the tool’s operation. However, if your file has no resource assignments at all, you will not get a result.
Currently, we support eight: 0/100, 25/75, 40/60, 50/50, Percent Complete, Level-of-Effort, Milestone Weights, and Milestone Weights with Percent Complete.
Baseline Roll-Up does not copy data into the baseline data locations. Rather it examines the current baseline resource information and aligns task information with it all through the schedule’s hierarchy. As a result, Baseline Roll-Up “corrects” the baseline to the time and amounts associated with your resource assignments. As a result, you can establish new tasks with baseline data that differs from their ETC data and Baseline Roll-Up will leave those differences intact.
After Baseline Roll-Up handle resource information, it rolls that information up to the associated tasks, and so it goes throughout the schedule hierarchy. For tasks lacking resource assignments, Baseline Roll-Up simply rolls up their baseline dates and durations. Those tasks are not ignored; the baseline data they have is processed.
EVM Analyses only reports on those analyses where it finds something that violates the analysis criteria. As a result, EVM Integrity only shows results where they may be a problem. In your case, it found no tasks in the schedule that violated the criteria for 5 of the analyses you selected.
Process BCWP calculates both BCWS and BCWP; their values are dependent upon the date associated with the calculation. Process BCWP is designed for weekly use and records your processing dates as the Status Date in Microsoft Project.